We are coming to the end of week 2 of the Studio build. We have been working long days to make the most of the weather and the fact that I am around to be the labourer for this period. It has gone well, that's not to say we didn't have problems but thankfully they have been dealt with and the Building Regs people are content, the builder even managed to get the floor lowered internally to give me an additional 6 inches of headroom for the lights which is great, My builder has been superb throughout he is a workaholic with a meticulous eye for detail! The next time Building Regs will be back is just before we start to put the roof on, lets hope the weather stays on our side.

Machinery arrives and the digging begins

Footing dig complete
The walls below ground

Ready to put the floor in

The walls rise above ground level after floor goes down

Site manager
No comments: